Things have moved along nicely out in Vaughan. The exterior of our home now has been bricked. It looks like things will work out for a move at the end of August.
We had our pre-drywall inspection last week, and the drywall was up soon thereafter. Canada Post have also acknowledged the new neighbourhood, by allocating our postal code!
- Wall frames are up, windows are in
- Pot light fixtures in the kitchen have been installed
- Central vacuum rough-in has been installed
- HVAC (heating vents) and vents for dryer and kitchen range hood are in
- Electrical wiring for plugs and lights is complete
- Wiring for cable (TV and internet) and telephone has been put int
- Plumbing for water and drainage is in
- Roof has been shingled
- Oak staircase has been installed
- Basement and garage floors have been poured
- Gas and electricity board and meters installed, but not yet hooked up
- Insulation has been put in the walls and they have been drywalled
- Bath-tubs have been put in
- Garage door has been put in
You can check out more photos of the progress on the building in the Thornhill Woods subdivision on Westolivia Trail: http://s207.photobucket.com/albums/bb84/thw-pics/